EXTON — Nearly two years after Sunoco Pipeline LP spilled drilling mud into Lake Marsh Creek and its tributaries, and more than a month past the company’s agreed deadline for remediation and restoration, local lawmakers have called for action. I am looking for

August 10 marks the second anniversary of the spill that dumped more than 20,000 gallons of drilling mud into streams, marshes and lakes during construction of Sunoco’s Mariner East II pipeline. A Consent Order and Agreement signed in December between the Department of Environmental Protection, the Department of Conservation and Natural Resources and Sunoco Pipeline LP, a subsidiary of Energy Transfer, allowed Sunoco to complete the dredging and to approve the dredged material. Move to a disposal facility and restore access and staging areas by July 1, 2022.

In documents submitted to DEP on June 23 and July 7, Sunoco attributed its failure to meet the agreed schedule to weather, an unexpected amount of debris on the lake bed, and significant We believe that this is due to a number of factors, including repeated equipment failures. Including the failure of the containment bag at the sediment dewatering station on July 1st. The biggest delay was attributed to him discovering two existing pipelines under the area the company planned to dredge, divers being brought in because the planned mechanized dredging could not be completed safely. .

“We are now more than a month past due, more than two years after the spill, and Sunoco has failed to complete the necessary repairs and restorations within the agreed-upon timeframes,” said State Representative Daniel. Friel Otten said.

“The excuse for their delay is what they could and had to explain in the planning process, especially the two pipelines that are clearly visible on the public map to anyone with a browser and internet connection. Presence and place.This operator continues to have complete disregard for the people and communities affected by their work.Senator Moose and I have met with the DEP for updates on the project and possible delays in progress. We have asked DEP to hold Sunoco accountable to the extent possible.”

Sunoco completed removal of the upper six inches of sediment from the affected portion of the lake in late July, and the 33-acre Ranger Cove section of Marsh Creek Lake is finally open to the public after nearly two years. rice field. A sediment dewatering station just outside Marsh Creek State Park is still a work in progress.

Sais Legislator Katie Muth said: After spilling more than 20,000 gallons of industrial waste into Lake Marsh Creek, they also failed to rehabilitate and restore the lake and aquatic habitat by her July 1 deadline. Clean drinking water for affected residents whose private wells were irreversibly contaminated by other reckless work during construction of the Mariner East II pipeline. “

“It is not surprising that Energy Transfer was able to successfully complete the pipeline in an expedited manner, even if rerouting was required. Energy Transfer means harm to waterways and communities. However, it is boldly clear that they have no interest or concern for anything other than securing their own interests.They were unable to complete the restoration on time, but this 2 We had a lot of cash on hand to buy our homes in order to be fully operational by the end of the quarter.The powers in Harrisburg on both sides of the aisle meant that corporate polluters wanted to keep their shareholders wealth. has allowed our community to become a victim zone for. If an entity cannot be an honest and respectful partner, it should not be allowed to do business within the Commonwealth.”

The Consent Order and Consent Form allow DEP to impose fines of $10,000 per day for each day past the July 1 deadline, and DEP can impose more severe penalties if necessary. Sunoco is listed at the beginning of the contract to guarantee the performance of the company’s obligations.

In a settlement with DEP and DCNR, Sunoco agreed to dredge and remove the contaminated sediment. Replaces damaged fish, wildlife and turtle habits. Restore coastlines and streamline buffers. The company also agreed to pay DCNR $4 million for lake and park improvements and $341,000 for DEP permit violations. Per the assessment and restoration plan, the lake should be restored to the same or better condition than it was before the August 2020 spill.

Sunoco missed a cleanup deadline at Marsh Creek State Park. Local lawmakers call for action – Daily Local

Source link Sunoco missed a cleanup deadline at Marsh Creek State Park. Local lawmakers call for action – Daily Local

Related Articles

Back to top button